Consumer Team — Build Dashboard

IDB + AGB · 01 Apr → 30 Jul 2026 · total scope 59 (IDB 39 · AGB 20) · IDB4 descoped

Burndown by delivery (linear timeline, priority order)

Aggregate remaining work to build, split by delivery · total scope 59 held from day one

Total remaining

26 / 59

% delivered

56%

Delivered (dev)

33 / 59

IDB remaining

6 / 39

AGB built

0 / 20

IDB1 closed at 27/30 (3 postponed) — its band bottoms at 3. IDB is nearly built (6 left: IDB1's 3 postponed, IDB2 1, IDB3 2). AGB's band is still flat at 20 — dev has begun (4 in the pipeline) but 0 completed, so nothing burns yet. Delivered (dev-tested) 33 of 59.

IDB burndown (all IDB, scope 39)

IDB pipeline milestones vs the burndown line · linear timeline · 01 Apr → 30 Jul

Total scope

39

Completed / tested

33 / 39

Remaining

6 / 39

Built (IDB)

34

Refined (IDB)

37

% complete

85%

Scope 39 (IDB4 removed). Completed 33 = IDB1 27 + IDB2 3 + IDB3 3. IDB1 exact from Ehab; IDB2/3 estimated. Only 6 remain — 3 of them IDB1 postponed, so the practical tail is IDB2 (1) + IDB3 (2).

IDB1 burndown (IDB1 only, scope 30 · source-exact)

IDB1 pipeline milestones vs the burndown line · linear timeline · 01 Apr → 30 Jul

Total scope

30

Completed / tested

27 / 30

Remaining

3 / 30

Built

27 / 30

Postponed

3

% complete

90%

IDB1 done at 27/30 — source-exact from Ehab. The remaining 3 are all postponed, so the burndown floors at 3 rather than 0. Nothing else in flight: 0 in dev, review, ready, or test.

AGB burndown (AGB only, scope 20)

Product writing & dev pipeline vs the build burndown · linear timeline · 01 Apr → 30 Jul

Total scope

20

Written (product)

16 / 20

In dev (now)

4

Built (dev)

0 / 20

Dev has finally started on AGB — 3 in development + 1 in review (the small teal step at 30 Jul), first movement ever. But still 0 built, so the burndown (black) holds flat at 20. Product writing (violet) is at 16/20. Once these clear testing the burndown will start to fall — this is the moment the AGB build began.

Status by delivery

Every story by current status, per delivery · snapshot at 30 Jul

Completed (dev)

33

IDB tail

6

AGB in dev

4

AGB written

16

Snapshot at 30 Jul. AGB build begun: 3 in development, 1 in review, 12 written-awaiting-dev, 4 not written, 0 done. IDB1 27 done, 3 postponed. IDB2 3 done (1 left — UAT). IDB3 3 done, 2 in progress (1 blocked).

Status flow (IDB only, 39 stories)

Every IDB story by status, over time · linear timeline (AGB dev just started — see AGB tab)

Completed

33

In flight

3

Postponed

3

Not started

0

IDB-only (39). Completed climbs to 33; the IDB1 pipeline has fully drained into Completed (27) and Postponed (3). Only IDB2/3's 3 remain in progress. June is the coarse Building band (reporting gap).

Team velocity (stories per month, IDB vs AGB, with average)

Product authoring vs engineering delivery, by calendar month · Apr → Jul 2026

Product avg

13.75 /mo

Eng avg

8.25 /mo

Delivered (dev)

33

AGB written

16

Bars split IDB (solid) vs AGB (faded). Product wrote 16 AGB stories in July — but engineering's July bar is still IDB-only (27): the 4 AGB now in dev aren't done, so they don't count as delivered yet. Wafaa's 16 is writing, not delivery. Averages over Apr–Jul: product 13.75/mo (55÷4), engineering 8.25/mo (33÷4).